Construction started on Segment 3 of the Front Beach Road CRA (Community Redevelopment Area) in early 2021. Segment 3 runs from the intersection of State Road 79 (Arnold Road) and Panama City Beach Parkway and includes Front Beach Road east to Lullwater Drive. This project includes the construction of a roundabout in the area shown above in what used to be called the Y at the Arnold/Front Beach Road intersection.
This 1.2-mile project includes new traffic lanes, turning lanes, a roundabout at 79 and Front Beach where the Y currently exists, landscaped medians, transit/bicycle lanes, sidewalks, lighting, signalization, landscaping, utility undergrounding, stormwater retention, signage and pavement markings.
The low bidder on the project was GAC Contractors, at approximately $28 million. C.W. Roberts took over the project not long after it began. Several change orders and inclement weather has extended the original 18-month contract.
Project Status
• Construction began in early 2021.
• Under construction, projected end date - Fall 2024.
• Utility, drainage and sewer line improvements ongoing.
• Water main extension west of Cabana Cay Circle approved by City Council.
• Pressure testing and sanitizing of water mains are ongoing.
• Working to complete utility conduit installation (FPL, AT&T, WOW) west of SR 79 to Cabana Cay Circle.
Click here for Segment 3 Fact Sheet.